Power Grid Corporation of India Ltd. vs. SPML Infra Limited, 2025 SCC OnLine Del 2541
Court can extend the mandate of the arbitral tribunal even if application for the same is filed post expiry of the time
17. Thus, in view of the legal position
enunciated in Rohan Builders (supra) and Ajay Protech
Pvt. Ltd. (supra), the fact that the application seeking extension of
time/mandate of the arbitral tribunal has been filed after the expiry of the
period of time contemplated in Section 29A(1) and 29A(3) of the A&C Act,
shall not be an impediment to this Court granting suitable extension of time to
the Arbitral Tribunal for the purpose of completion of arbitral proceedings.
The Bar Council of India does not permit solicitation of work and advertising by legal practitioners and advocates. By accessing the Litigating Hand website (our website), the user acknowledges that:
The user wishes to gain more information about us for his/her information and use. He/She also acknowledges that there has been no attempt by us to advertise or solicit work.
Any information obtained or downloaded by the user from our website does not lead to the creation of the client – attorney relationship between the Firm and the user.
None of the information contained in our website amounts to any form of legal opinion or legal advice.
Our website uses cookies to improve your user experience. By using our site, you agree to our use of cookies. To find out more, please see our Cookies Policy & Privacy Policy
All information contained in our website is the intellectual property of the Firm.