Union of India vs. Manraj Enterprises, Civil Appeal No. 6592 of 2021

No interest awardable by arbitrator when contract forbids it

Brief: The Hon’ble Supreme Court in the instant petition set aside awarding of pendente lite and future interest by arbitrator despite the agreement forbidding award of interest. The Hon’ble Court held that Section 31(7) of the 1996 Act, by using the words “unless otherwise agreed by the parties” categorically specifies that the arbitrator is bound by the terms of the contract insofar as award of interest from the date of cause of action to date of the award is concerned.

RELEVANT PARAGRAPH

6.1 The short question which is posed for the consideration of this Court is in view of the specific clause 16(2) of the GCC, whether the contractor is entitled to any interest pendente lite on the amounts payable to the contractor other than upon the earnest money or the security deposit.

8. In the case of Bright Power Projects (India) (P) Ltd. (supra), while considering pari materia clause with clause 16(2) of the GCC, a three Judge Bench of this Court has held that when the parties to the contract agree to the fact that interest would not be awarded on the amount payable to the contractor under the contract, they are bound by their understanding and having once agreed that the contractor would not claim any interest on the amount to be paid under the contract, he could not have claimed interest either before a civil court or before an Arbitral Tribunal……..

 

8.1. In the said decision, this Court also considered Section 31(7)(a) of the 1996 Act. It is specifically observed and held that Section 31(7) of the 1996 Act, by using the words “unless otherwise agreed by the parties” categorically specifies that the arbitrator is bound by the terms of the contract insofar as award of interest from the date of cause of action to date of the award is concerned. It is further observed and held that where the parties had agreed that no interest shall be payable, the Arbitral Tribunal cannot award interest. Thus, the aforesaid decision of a three Judge Bench of this Court is the answer to the submission made on behalf of the respondent that despite the bar under clause 16(2) which is applicable to the parties, the Arbitral Tribunal is not bound by the same. Therefore, the contention raised on behalf of the respondent that de hors the bar under clause 16(2), the Arbitral Tribunal independently and on equitable ground and/or to do justice can award interest pendente lite or future interest has no substance and cannot be accepted. Once the contractor agrees that he shall not be entitled to interest on the amounts payable under the contract, including the interest upon the earnest money and the security deposit as mentioned in clause 16(2) of the agreement/contract between the parties herein, the arbitrator in the arbitration proceedings being the creature of the contract has no power to award interest, contrary to the terms of the agreement/contract between the parties and contrary to clause 16(2) of the agreement/contract in question in this case.